- Dock 4 Column and Door RepairFinish forecast 5 days past baseline · W8x31 steel column: Delayed · Change order waiting on the client since Nov 12
- Kentwood Dental Office BuildoutFinish forecast 7 days past baseline · No published update in 9 days
- Freezer Building ExpansionFinish forecast 7 days past baseline · Rooftop refrigeration unit RTU-2: Backordered
- Plant 2 Office ExpansionLakeshore Precision Plastics · Commercial renovationPM Dana KowalskiPhase Mechanical, electrical, plumbing and fire protection56%On scheduleFinish Jan 30, 2027Updated today
- Dock 4 Column and Door RepairLakeshore Precision Plastics · Emergency repairPM Marcus BellPhase Project preparation and procurement37%At riskFinish Dec 1, 2026Updated 2 days ago
- Kentwood Dental Office BuildoutRiverbend Dental Group · Medical and dental spacePM Dana KowalskiPhase Permitting and agency approvals25%At riskFinish Mar 13, 2027Updated 9 days ago
- Wyoming Office RefreshRiverbend Dental Group · Commercial renovationPM Marcus BellPhase Complete100%CompleteFinish Sep 26, 2027Updated 44 days ago
- Freezer Building ExpansionCascade Cold Storage · Industrial new constructionPM Marcus BellPhase Sitework, underground utilities and structure30%At riskFinish May 15, 2027Updated yesterday
- Warehouse A Roof ReplacementCascade Cold Storage · Commercial roofingPM Dana KowalskiPhase Project preparation and procurement20%On holdFinish May 15, 2027Updated 24 days ago
No projects match.
Next 14 days, all projects
Work, inspections and deliveries- Nov 14Drywall and insulation: Second floor hang Friday, then tape and finish. · Plant 2 Office Expansion
- Nov 14Excavation / sitework: Sanitary lateral and building pad compaction tests. · Freezer Building Expansion
- Nov 14Inspection: Compaction testing 11/14 · Freezer Building Expansion
- Nov 15Concrete: South footings Saturday 11/15 (weather permitting). · Freezer Building Expansion
- Nov 17Electrical: Panel labels, then trim-out after paint. · Plant 2 Office Expansion
- Nov 17Inspection: Rough electrical passed 11/10 · Plant 2 Office Expansion
- Nov 18HVAC: Branch ducts and diffusers. · Plant 2 Office Expansion
- Nov 18Delivery: Dock door panels and track · Dock 4 Column and Door Repair
- Nov 19Delivery: W8x31 steel column · Dock 4 Column and Door Repair
- Nov 20Structural / steel: Set the new column, then weld the base plate. · Dock 4 Column and Door Repair
- Nov 20Inspection: Engineer's field review after the column is set · Dock 4 Column and Door Repair
- Nov 24Ceilings and flooring: Ceiling grid starts after drywall finish. · Plant 2 Office Expansion
- Nov 24Specialty: overhead door: New track and panels on Dock 4 after the column. · Dock 4 Column and Door Repair