Client portal
Welcome back, Erin
Lakeshore Precision Plastics · Facility manager
2 decisions are waiting on you
- On scheduleUpdated today
Plant 2 Office Expansion
4120 Fernbrook Ave NW, Walker, MI
Now: Mechanical, electrical, plumbing and fire protection
“First floor drywall is hung. Second floor starts Friday morning; the stairwell door stays closed while they work.”
- Forecast finish
- Jan 30, 2027
- Project manager
- Dana Kowalski
- Deliveries
- On time
- Your decisions
- 1
- At riskUpdated 2 days ago
Dock 4 Column and Door Repair
4120 Fernbrook Ave NW, Walker, MI
Now: Project preparation and procurement
“The fabricator moved the column to Wednesday 11/19. Shoring stays in; Dock 4 stays closed until then.”
- Forecast finish
- Dec 1, 2026
- Project manager
- Marcus Bell
- Deliveries
- 1 late
- Your decisions
- 1
Coming up
- To approvePower shutdown proposed: Sat 11/22, 6–9 am, Panel 2B (offices and break room) · Plant 2 Office Expansion
- Nov 14Drywall and insulation: Second floor hang Friday, then tape and finish. · Plant 2 Office Expansion
- Nov 17Electrical: Panel labels, then trim-out after paint. · Plant 2 Office Expansion
- Nov 18HVAC: Branch ducts and diffusers. · Plant 2 Office Expansion
- Nov 20Structural / steel: Set the new column, then weld the base plate. · Dock 4 Column and Door Repair
- Nov 24Ceilings and flooring: Ceiling grid starts after drywall finish. · Plant 2 Office Expansion