Plant 2 Office Expansion
Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI
- Phase
- 6 of 11
- Forecast finish
- Jan 30, 2027
- Project manager
- Dana Kowalski
- Last updated
- today
Done
5 of 11
Last: Demolition and debris removal
Now
Mechanical, electrical, plumbing and fire protection
Electrical, HVAC, Drywall and insulation
Next
Nov 14
Drywall and insulation: Second floor hang Friday, then tape and finish.
Schedule
On schedule
Finish Jan 30, 2027.
Materials
On time
Every delivery is due before it's needed.
From you
1 decision
Milestones
Full schedule →- Preconstruction and project assessment100%
- Stamped construction plans100%
- Permitting and agency approvals100%
- Mobilization and site protection100%
- Demolition and debris removal100%
- Mechanical, electrical, plumbing and fire protection85%
- Building enclosure and interior construction55%
- Finishes and equipment0%
- Testing, inspections and commissioning0%
- Punch list and final corrections0%
- Final inspection, closeout and turnover0%
Latest updates
Published by GRCFirst floor drywall is hung. Second floor starts Friday morning; the stairwell door stays closed while they work.
- Photo
- Photo
- Photo
Rough electrical inspection passed with no corrections.
- Photo
Sprinkler heads relocated and pressure tested. Ceiling can close up.
- Photo
- Photo