Plant 2 Office Expansion
Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI
- Phase
- 6 of 11
- Forecast finish
- Jan 30, 2027
- Project manager
- Dana Kowalski
- Last updated
- today
Demolition
CompleteGRC crew
100%- Last activity
- Oct 9
- Next work
- Done
Done: Old offices and ceiling removed, debris hauled.
Electrical
In progressNorthgate Electric
90%- Last activity
- Nov 12
- Next work
- Nov 17
Done: Rough-in complete and inspected.
Next: Panel labels, then trim-out after paint.
Inspection: Rough electrical passed 11/10
HVAC
In progressSummit Mechanical
60%- Last activity
- Nov 11
- Next work
- Nov 18
Done: Main trunk extended into the new wing.
Next: Branch ducts and diffusers.
Fire protection
CompleteGreat Lakes Fire Sprinkler
100%- Last activity
- Nov 6
- Next work
- Done
Done: Heads relocated for the new walls.
Inspection: Hydro test passed 11/6
Carpentry and framing
CompleteGRC crew
100%- Last activity
- Nov 5
- Next work
- Done
Done: All metal stud walls framed.
Drywall and insulation
In progressWest Michigan Interiors
40%- Last activity
- Nov 13
- Next work
- Nov 14
Done: First floor hung.
Next: Second floor hang Friday, then tape and finish.
Ceilings and flooring
ScheduledGRC crew
0%- Last activity
- None yet
- Next work
- Nov 24
Next: Ceiling grid starts after drywall finish.
Painting
Not startedBrightline Painting
0%- Last activity
- None yet
- Next work
- Dec 8
Next: Two coats, colors per finish schedule.