On schedule

Plant 2 Office Expansion

Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI

Phase
6 of 11
Forecast finish
Jan 30, 2027
Project manager
Dana Kowalski
Last updated
today
56%verified
1 decision needs you Choose the carpet tile color for the new offices, due Nov 21 →

Schedule

Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.
  1. Preconstruction and project assessment · 3% of scope100%
    Planned finish
    Aug 8
    Forecast
    Aug 8
    Variance
    On time
  2. Stamped construction plans · 5% of scope100%
    Planned finish
    Aug 29
    Forecast
    Aug 27
    Variance
    2 d early
  3. Permitting and agency approvals · 5% of scope100%
    Planned finish
    Sep 19
    Forecast
    Sep 22
    Variance
    3 d late
  4. Mobilization and site protection · 4% of scope100%
    Planned finish
    Sep 26
    Forecast
    Sep 26
    Variance
    On time
  5. Demolition and debris removal · 8% of scope100%
    Planned finish
    Oct 10
    Forecast
    Oct 9
    Variance
    1 d early
  6. Mechanical, electrical, plumbing and fire protection · 20% of scope85%
    Planned finish
    Nov 21
    Forecast
    Nov 21
    Variance
    On time
    • ✓Electrical rough-in
    • ✓Sprinkler heads relocated
    • HVAC duct to new offices
  7. Building enclosure and interior construction · 25% of scope55%
    Planned finish
    Dec 12
    Forecast
    Dec 12
    Variance
    On time
    • ✓Metal stud framing
    • Drywall hang, 2nd floor
    • Drywall finish
  8. Finishes and equipment · 18% of scope0%
    Planned finish
    Jan 9
    Forecast
    Jan 9
    Variance
    On time
  9. Testing, inspections and commissioning · 6% of scope0%
    Planned finish
    Jan 16
    Forecast
    Jan 16
    Variance
    On time
  10. Punch list and final corrections · 3% of scope0%
    Planned finish
    Jan 23
    Forecast
    Jan 23
    Variance
    On time
  11. Final inspection, closeout and turnover · 3% of scope0%
    Planned finish
    Jan 30
    Forecast
    Jan 30
    Variance
    On time