At risk
Dock 4 Column and Door Repair
Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI
- Phase
- 3 of 5
- Forecast finish
- Dec 1, 2026
- Project manager
- Marcus Bell
- Last updated
- 2 days ago
CO-2: replace the damaged bollard at Dock 4 ($1,850)
Change orderFound bent at its base during the assessment. Photos in Files.
- Due
- Nov 12, 2026
- Effect
- Can be installed with the column work if approved this week.
- Who can decide
- Chris Lang
This records your decision with your name and the time. It is not a signature; contract changes are signed separately.