At risk

Dock 4 Column and Door Repair

Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI

Phase
3 of 5
Forecast finish
Dec 1, 2026
Project manager
Marcus Bell
Last updated
2 days ago
37%verified
1 decision needs you CO-2: replace the damaged bollard at Dock 4 ($1,850), due Nov 12 →

Schedule

Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.
  1. Preconstruction and project assessment · 10% of scope100%
    Planned finish
    Oct 24
    Forecast
    Oct 24
    Variance
    On time
  2. Stamped construction plans · 15% of scope100%
    Planned finish
    Oct 31
    Forecast
    Nov 3
    Variance
    3 d late
  3. Project preparation and procurement · 20% of scope60%
    Planned finish
    Nov 14
    Forecast
    Nov 19
    Variance
    5 d late

    Delay, 5 days: Replacement steel column delayed at the fabricator. Next: Temporary shoring stays in; fabricator promised Wednesday 11/19.

  4. Sitework, underground utilities and structure · 35% of scope0%
    Planned finish
    Nov 21
    Forecast
    Nov 26
    Variance
    5 d late
  5. Final inspection, closeout and turnover · 20% of scope0%
    Planned finish
    Nov 26
    Forecast
    Dec 1
    Variance
    5 d late