At risk
Dock 4 Column and Door Repair
Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI
- Phase
- 3 of 5
- Forecast finish
- Dec 1, 2026
- Project manager
- Marcus Bell
- Last updated
- 2 days ago
W8x31 steel column
DelayedKent Steel Fabricators
- Requested
- Approved
- Ordered
- Confirmed
- In production
- Shipped
- Delivered
- Installed
- Ordered
- Nov 4
- Expected
- Nov 19
- Needed on site
- Nov 14
Schedule effect: Finish moves about 5 days; Dock 4 stays out of service until then.
Dock door panels and track
ShippedOverhead Door of West Michigan
- Requested
- Approved
- Ordered
- Confirmed
- In production
- Shipped
- Delivered
- Installed
- Ordered
- Nov 3
- Expected
- Nov 18
- Needed on site
- Nov 24