Built on WIX Headless
Commercial and industrial general contractor, Grand Rapids, MI. MI Builders License 262100253Emergency repairsVendor setup

Demo Made-up companies, people and numbers. Nothing is saved.

At riskGRC view

Freezer Building Expansion

Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI

Phase
4 of 7
Forecast finish
May 15, 2027
Project manager
Marcus Bell
Last updated
yesterday
30%verified
  • Insulated metal wall panels

    Ordered

    Panel manufacturer

    1. Requested
    2. Approved
    3. Ordered
    4. Confirmed
    5. In production
    6. Shipped
    7. Delivered
    8. Installed
    Ordered
    Oct 20
    Expected
    Jan 5
    Needed on site
    Jan 12
  • Rooftop refrigeration unit RTU-2

    Backordered

    Refrigeration supplier

    1. Requested
    2. Approved
    3. Ordered
    4. Confirmed
    5. In production
    6. Shipped
    7. Delivered
    8. Installed
    Ordered
    Sep 30
    Expected
    Mar 30
    Needed on site
    Mar 20

    Schedule effect: About 10 days on start-up; the PM is pricing an alternate unit.

CallGet a quote