At riskGRC view
Freezer Building Expansion
Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI
- Phase
- 4 of 7
- Forecast finish
- May 15, 2027
- Project manager
- Marcus Bell
- Last updated
- yesterday
Schedule
Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.- Stamped construction plans · 6% of scope100%
- Planned finish
- Aug 15
- Forecast
- Aug 15
- Variance
- On time
- Permitting and agency approvals · 6% of scope100%
- Planned finish
- Sep 12
- Forecast
- Sep 12
- Variance
- On time
- Mobilization and site protection · 4% of scope100%
- Planned finish
- Sep 26
- Forecast
- Sep 26
- Variance
- On time
- Sitework, underground utilities and structure · 30% of scope45%
- Planned finish
- Dec 19
- Forecast
- Dec 31
- Variance
- 12 d late
Delay, 12 days: Two weeks of rain in October. Next: Weekend concrete pours through November.
- Building enclosure and interior construction · 30% of scope0%
- Planned finish
- Mar 20
- Forecast
- Mar 27
- Variance
- 7 d late
- Mechanical, electrical, plumbing and fire protection · 14% of scope0%
- Planned finish
- Apr 17
- Forecast
- Apr 24
- Variance
- 7 d late
- Final inspection, closeout and turnover · 10% of scope0%
- Planned finish
- May 8
- Forecast
- May 15
- Variance
- 7 d late