At riskGRC view
Dock 4 Column and Door Repair
Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI
- Phase
- 3 of 5
- Forecast finish
- Dec 1, 2026
- Project manager
- Marcus Bell
- Last updated
- 2 days ago
Structural / steel
WaitingKent Steel Fabricators
10%- Last activity
- Nov 7
- Next work
- Nov 20
Done: Shop drawings approved.
Next: Set the new column, then weld the base plate.
Column delayed at the fabricator (new date 11/19).
Inspection: Engineer's field review after the column is set
Specialty: overhead door
ScheduledOverhead Door of West Michigan
0%- Last activity
- None yet
- Next work
- Nov 24
Next: New track and panels on Dock 4 after the column.