On scheduleGRC view
Plant 2 Office Expansion
Lakeshore Precision Plastics · 4120 Fernbrook Ave NW, Walker, MI
- Phase
- 6 of 11
- Forecast finish
- Jan 30, 2027
- Project manager
- Dana Kowalski
- Last updated
- today
Schedule
Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.- Preconstruction and project assessment · 3% of scope100%
- Planned finish
- Aug 8
- Forecast
- Aug 8
- Variance
- On time
- Stamped construction plans · 5% of scope100%
- Planned finish
- Aug 29
- Forecast
- Aug 27
- Variance
- 2 d early
- Permitting and agency approvals · 5% of scope100%
- Planned finish
- Sep 19
- Forecast
- Sep 22
- Variance
- 3 d late
- Mobilization and site protection · 4% of scope100%
- Planned finish
- Sep 26
- Forecast
- Sep 26
- Variance
- On time
- Demolition and debris removal · 8% of scope100%
- Planned finish
- Oct 10
- Forecast
- Oct 9
- Variance
- 1 d early
- Mechanical, electrical, plumbing and fire protection · 20% of scope85%
- Planned finish
- Nov 21
- Forecast
- Nov 21
- Variance
- On time
- ✓Electrical rough-in
- ✓Sprinkler heads relocated
- HVAC duct to new offices
- Building enclosure and interior construction · 25% of scope55%
- Planned finish
- Dec 12
- Forecast
- Dec 12
- Variance
- On time
- ✓Metal stud framing
- Drywall hang, 2nd floor
- Drywall finish
- Finishes and equipment · 18% of scope0%
- Planned finish
- Jan 9
- Forecast
- Jan 9
- Variance
- On time
- Testing, inspections and commissioning · 6% of scope0%
- Planned finish
- Jan 16
- Forecast
- Jan 16
- Variance
- On time
- Punch list and final corrections · 3% of scope0%
- Planned finish
- Jan 23
- Forecast
- Jan 23
- Variance
- On time
- Final inspection, closeout and turnover · 3% of scope0%
- Planned finish
- Jan 30
- Forecast
- Jan 30
- Variance
- On time