At riskGRC view
Kentwood Dental Office Buildout
Riverbend Dental Group · 2875 Hillcrest Dr SE, Kentwood, MI
- Phase
- 3 of 6
- Forecast finish
- Mar 13, 2027
- Project manager
- Dana Kowalski
- Last updated
- 9 days ago
Schedule
Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.- Preconstruction and project assessment · 5% of scope100%
- Planned finish
- Sep 12
- Forecast
- Sep 12
- Variance
- On time
- Architectural and engineering development · 15% of scope100%
- Planned finish
- Oct 10
- Forecast
- Oct 15
- Variance
- 5 d late
- Permitting and agency approvals · 10% of scope50%
- Planned finish
- Nov 7
- Forecast
- Nov 14
- Variance
- 7 d late
Delay, 7 days: Plan review asked for medical gas details. Next: Engineer resubmitted 11/3.
- Building enclosure and interior construction · 40% of scope0%
- Planned finish
- Jan 23
- Forecast
- Jan 30
- Variance
- 7 d late
- Finishes and equipment · 20% of scope0%
- Planned finish
- Feb 20
- Forecast
- Feb 27
- Variance
- 7 d late
- Final inspection, closeout and turnover · 10% of scope0%
- Planned finish
- Mar 6
- Forecast
- Mar 13
- Variance
- 7 d late