By Grand Rapids Construction. Updated November 12, 2026.
Check that they priced the same drawings
Ask each bidder which drawing set and date they priced. A bid built on an earlier sketch is not comparable with one built on the permit set.
Items that are often missing
- Demolition and disposal
- Permit fees and plan review
- Engineering or architectural drawings
- Fire sprinkler and alarm changes caused by new walls or ceilings
- Electrical, plumbing and HVAC changes
- After-hours or phased work in an occupied building
- Dust control and protection of your space
- Final cleaning, inspections and closeout documents
Allowances are not prices
An allowance is a placeholder for something not yet chosen, such as flooring at a stated amount per square foot. If your choice costs more, you pay the difference. A proposal with low allowances can look cheaper and finish more expensive. Ask what each allowance is based on.
How unknowns and changes are handled
Every renovation has concealed conditions. Look for how the proposal says they are documented and priced, what markup applies to changes, and who can approve them. A clear change process is worth more than a low number with none.
Schedule assumptions
Check working hours, the number of phases, lead times for long-delivery items and what the schedule assumes you will provide: access, decisions, owner-supplied equipment. A shorter schedule that assumes an empty building is not shorter if your building is occupied.