On hold
Warehouse A Roof Replacement
Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI
- Phase
- 2 of 4
- Forecast finish
- May 15, 2027
- Project manager
- Dana Kowalski
- Last updated
- 24 days ago
Schedule
Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.- Preconstruction and project assessment · 20% of scope100%
- Planned finish
- Oct 17
- Forecast
- Oct 17
- Variance
- On time
- Project preparation and procurement · 20% of scope0%
- Planned finish
- Mar 27
- Forecast
- Mar 27
- Variance
- On time
- Building enclosure and interior construction · 50% of scope0%
- Planned finish
- May 1
- Forecast
- May 1
- Variance
- On time
- Final inspection, closeout and turnover · 10% of scope0%
- Planned finish
- May 15
- Forecast
- May 15
- Variance
- On time