At risk
Freezer Building Expansion
Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI
- Phase
- 4 of 7
- Forecast finish
- May 15, 2027
- Project manager
- Marcus Bell
- Last updated
- yesterday
Done
3 of 7
Last: Mobilization and site protection
Now
Sitework, underground utilities and structure
Excavation / sitework, Concrete
Next
Nov 14
Excavation / sitework: Sanitary lateral and building pad compaction tests.
Schedule
At risk
Finish May 15, 2027 (planned May 8). Two weeks of rain in October.
Materials
1 late
Rooftop refrigeration unit RTU-2: About 10 days on start-up; the PM is pricing an alternate unit.
From you
Nothing
GRC doesn't need anything from you right now.
Milestones
Full schedule →- Stamped construction plans100%
- Permitting and agency approvals100%
- Mobilization and site protection100%
- Sitework, underground utilities and structure45%
- Building enclosure and interior construction0%
- Mechanical, electrical, plumbing and fire protection0%
- Final inspection, closeout and turnover0%
Latest updates
Published by GRCStorm sewer complete and backfilled. Compaction tests Friday.
- Photo
- Photo