At risk
Freezer Building Expansion
Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI
- Phase
- 4 of 7
- Forecast finish
- May 15, 2027
- Project manager
- Marcus Bell
- Last updated
- yesterday
Insulated metal wall panels
OrderedPanel manufacturer
- Requested
- Approved
- Ordered
- Confirmed
- In production
- Shipped
- Delivered
- Installed
- Ordered
- Oct 20
- Expected
- Jan 5
- Needed on site
- Jan 12
Rooftop refrigeration unit RTU-2
BackorderedRefrigeration supplier
- Requested
- Approved
- Ordered
- Confirmed
- In production
- Shipped
- Delivered
- Installed
- Ordered
- Sep 30
- Expected
- Mar 30
- Needed on site
- Mar 20
Schedule effect: About 10 days on start-up; the PM is pricing an alternate unit.