At risk
Freezer Building Expansion
Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI
- Phase
- 4 of 7
- Forecast finish
- May 15, 2027
- Project manager
- Marcus Bell
- Last updated
- yesterday
Excavation / sitework
In progressByron Excavating
70%- Last activity
- Nov 12
- Next work
- Nov 14
Done: Mass grading and storm sewer.
Next: Sanitary lateral and building pad compaction tests.
Inspection: Compaction testing 11/14
Concrete
In progressRidge Concrete
25%- Last activity
- Nov 8
- Next work
- Nov 15
Done: North footings poured.
Next: South footings Saturday 11/15 (weather permitting).
Roofing / building envelope
Not startedInsulated panel installer (TBD)
0%- Last activity
- None yet
- Next work
- Jan 12
Next: Panel shop drawings due 12/1.