At risk

Freezer Building Expansion

Cascade Cold Storage · 9600 Coldwater Way, Byron Center, MI

Phase
4 of 7
Forecast finish
May 15, 2027
Project manager
Marcus Bell
Last updated
yesterday
30%verified

Schedule

Progress counts only work checked in the field, weighted by its share of the job. A date passing never marks a milestone done.
  1. Stamped construction plans · 6% of scope100%
    Planned finish
    Aug 15
    Forecast
    Aug 15
    Variance
    On time
  2. Permitting and agency approvals · 6% of scope100%
    Planned finish
    Sep 12
    Forecast
    Sep 12
    Variance
    On time
  3. Mobilization and site protection · 4% of scope100%
    Planned finish
    Sep 26
    Forecast
    Sep 26
    Variance
    On time
  4. Sitework, underground utilities and structure · 30% of scope45%
    Planned finish
    Dec 19
    Forecast
    Dec 31
    Variance
    12 d late

    Delay, 12 days: Two weeks of rain in October. Next: Weekend concrete pours through November.

  5. Building enclosure and interior construction · 30% of scope0%
    Planned finish
    Mar 20
    Forecast
    Mar 27
    Variance
    7 d late
  6. Mechanical, electrical, plumbing and fire protection · 14% of scope0%
    Planned finish
    Apr 17
    Forecast
    Apr 24
    Variance
    7 d late
  7. Final inspection, closeout and turnover · 10% of scope0%
    Planned finish
    May 8
    Forecast
    May 15
    Variance
    7 d late